Project “Construction of four compressor stations on Beineu-Bozoy-Shymkent gas pipeline”
Project duration: 2018-2020.
The cost is 192,747 million tenge without VAT.
The project is implemented by Goodwin Capital LLP, as part of measures to increase the annual capacity of the Beineu-Bozoi-Shymkent gas pipeline from 10 to 15 billion m³.
In February 2019, Aral, Korkyt Ata and Turkestan compressor stations were commissioned on the Bozoi-Shymkent section of the gas pipeline. The Beineu-Bozoi-Shymkent gas pipeline capacity has been increased to 13 billion m³ per year.
On April 29, 2020, the last fourth compressor station “1A” was commissioned at the Beineu-Bozoy section of the gas pipeline. With the commissioning of the fourth compressor station, KTG completed the implementation of a large-scale project to increase the throughput capacity of the Beineu-Bozoy-Shymkent gas pipeline to 15 billion m3/year, ensuring high reliability of gas supplies to the domestic market, as well as for export.