Project “Construction of the Beineu-Bozoy-Shymkent gas pipeline”
Project duration: 2011-2021
Cost – 689,201 million tenge without VAT.
The purpose of the project is to ensure stable gas supplies to the southern regions of the Republic of Kazakhstan, reduce dependence on imported gas and ensure energy security of the Republic of Kazakhstan.
The gas pipeline route, installed by Goodwin Capital LLP, runs through the territory of Mangistau, Aktobe, Kyzylorda and Turkestan regions and has the following main technical characteristics:
Phase 1: 2012-2019, capacity up to 6 billion m³ per year;
Stage 2: 2013-2019, capacity up to 10 billion m³ per year;
Stage 3: 2018-2022, capacity up to 15 billion m³ per year.
The linear part of the gas pipeline with the length of 1,450 km (single-line version), a shift camp, gas metering stations, route road, two compressor stations Bozoy and Karaozek and four additional compressor stations Turkestan, Aral, Korkyt-Ata, 1 “A” built by Goodwin Capital LLP were commissioned.
In 2020, the following activities were carried out:
* development of design and estimate documentation “Increase of throughput capacity of “Beineu-Bozoy-Shymkent” gas pipeline up to 15 billion m3/year” was completed;
* the purchase of the Turkestan compressor station was made.